An Energy from Waste facility uses thermal technology to convert waste that would otherwise go to landfill into steam, which drives turbines to generate electricity.


In 2015 the Department of Planning and Environment received and exhibited a development application and environmental impact statement (EIS) for an Energy from Waste facility at Eastern Creek. Since mid-2015, a considerable number of issues and questions around the proposal were raised by the independent experts the Department engaged, other government agencies, and the community.


In late 2016 through to 1 March 2017 the Department exhibited an amended EIS (part A, 7.7Mb and part B, 8Mb) which included a Response to Submissions Report (RTS) from the applicant:

Appendix HH1 - Response to community submissions

Appendix HH2 – Response to agency submissions

Appendix HH3 – Response to Flora and Fauna Issues


Feedback from the exhibition of the amended EIS included concerns about health risks, air quality, location of the facility and the suitability of the site. The applicant must now prepare a new RTS to address the concerns raised and to support an amended development application for the construction and operation of only Stage 1 of the proposal to process 552,500 tonnes of waste per annum.

 

Timeline for Eastern Creek Energy from Waste development application

Date Activity

December

2013

Director General Requirement’s issued to inform preparation of Environmental Impact Statement (EIS)

January

2014

Applicant commence preparation of EIS and stakeholder consultation

November

2014

Secretary approves Engagement of Independent Experts in human health risk and energy from waste technology

May

2015

EIS lodged with Department for Public Exhibition and review by Independent Experts 

July

2015

Applicant review of submissions and preparation of Response to Submissions

November

2015

Response to Submissions lodged with Department

December

2015

Review of Response to Submissions by Department, key government agencies and Independent Experts

February

2016

Gap analysis undertaken by Independent Experts on behalf of Department

June

2016

Applicant review gap analysis and commence preparation of amended application

December

2016

Amended EIS lodged with Department for Public Exhibition and review by key government agencies and Independent Experts

March

2017

Applicant review of submissions

July

2017

Applicant lodged Response to Submissions Report

August
2017

 Review of Response to Submissions Report by Department. Department requests Applicant to revise Response to Submissions Report to suitably support an amended development application for only Stage 1 of the proposal. 
October 
2017
Applicant to lodge amended application for Stage 1 only and revised Response to Submissions Report.

 