Department of Planning

Current Media Releases

 

Media Releases Home

Planning Home

Media Release - Department of Planning

Sydney: 25 July 2008


BLACK SPRINGS WIND FARM GETS GREEN LIGHT

The NSW Government has approved a $32.6 million wind farm at Black Springs in state’s central west that is expected to save 43,660 tonnes of greenhouse gas emissions each year.

The Department of Planning’s Executive Director of Major Project Assessment, Chris Wilson said the project involves the construction of nine turbines, a substation, control room and associated access roads on existing farming properties that shall continue to be used for sheep and cattle grazing.

“The Black Springs Wind Farm is consistent with State Plan priorities for a reliable electricity supply with increased use of renewable energy,” Mr Wilson said.

“After consideration of various locations in NSW, the site in the Oberon local government area was selected by the applicant due to sufficient local energy demand, suitable wind conditions and available infrastructure.

“The project will generate 32 construction stage jobs and one full-time operational position, and potentially fuel investment in the local area.

“Its greenhouse gas savings will be equivalent of taking around 10,000 cars off the road.”

After an extended exhibition period of six weeks, 100 submissions were received by the Department raising issues including visual impacts, noise impacts, potential alterations to aircraft movements and effects on land values.

Following a meeting with the Minister for Planning and representatives of the local community in October 2007, the Department sought independent advice in relation to operational noise and visual impact issues.

Independent noise experts found that noise goals could be achieved with the help of appropriate management and mitigation measures, including restricting the use of a turbine.

Independent visual experts found that overall the landscape was able to accommodate any changes resulting from the windfarm.

The recommendations resulting from the assessment have been incorporated into the Minister’s conditions, which include:

• The imposition of strict noise limits for project operation, including the restricted use of Turbine 1 depending on wind conditions;

• The provision, at the request of any landowner within 4km of the site, of adequate vegetative screening on those properties;

• A requirement to negotiate with State Forests NSW in order to ensure a vegetative barrier is retained either within the existing forest or by new vegetative screenings if the forest is cleared;

• The implementation of detailed Construction and Operation Environmental Management Plans addressing noise and landscape management; and

• The development of a Community Enhancement Program in consultation with the local council, including an annual contribution of $15,000 to the Program.


 

MEDIA CONTACTS:
Department of Planning
Media Unit (02) 9228 6274
23-33 Bridge Street
SYDNEY NSW 2000
Facsimile (02) 9228 6564

Top of Page List of Media Releases

© NSW Department of Planning