- Share:
Find out more about each stage of the development consent and construction approval processes. This section will take you through each stage, people’s roles and what’s involved to get your Occupation Certificate then celebrate and move in.
Page last updated: 01/04/2020
Stage 1 – Pre-lodgement (Getting it right at the start)
If you get the front end right you are likely to have a simple DA process.
Continue to Stage 1Stage 2 – Lodgement and initial administration by council of your application
When you have filled out all the required forms you can lodge your application with council.
Continue to Stage 2Stage 3 – Assessment (What happens to my DA now?)
The site must be inspected, applicants and neighbours engaged, reports drafted and recommendations made.
Continue to Stage 3Stage 4 – Determination (The Decision)
There are three possible outcomes for a DA: Development consent, DA refusal, deferred commencement consent.
Continue to Stage 4Stage 5 – Get your Construction Certificate and organise construction
Before you can start building you must do four things: Get a Construction Certificate, appoint a Principal Certifying Authority (PCA), give the council and the PCA two days’ notice before you start work, and complete any works.
Continue to Stage 5Stage 6 – Get your Occupation Certificate and celebrate
The OC authorises the occupation and use of a new building or building section. For staged works, an Interim OC may be issued which allows you to occupy the completed part of the building.
Continue to Stage 6