Stage 1 Concept

The concept proposals for over station developments above both the northern and southern entrances to the new Pitt Street Metro station were approved in June 2019.

A full list of the conditions of consent is available at Major Projects.

Concept modification approved

A modification application to amend the approved Stage 1 concept building envelope for Pitt Street North was approved in February 2021 as part of the Horizon Projects program.

The approved application consents to:

  • amend the building envelope to increase the podium height to align with the Masonic Building on Castlereagh Street and the National Building on Pitt Street
  • allow for protrusions (up to a maximum of 600mm) beyond the approved building envelope for sunshades, planters and balustrades
  • increase the maximum gross floor area across the site to 55,743 m2 (from 50,310 m2)
  • amend the approved Design Guidelines in respect to podium heights and building setbacks.

For more information about the modification application visit Major Projects.

Next steps

Detailed design, construction and operation of Pitt St North OSD are subject to a Stage 2 development application. The application was approved in February 2021.

For more information about the Pitt Street North concept application, go Major Projects.

To find out more about this project go to: