Final plans for North Appin (Part) Precinct

The NSW Government has finalised planning for the North Appin (Part) Precinct, rezoning land to support around 3,000 homes and around 670 local jobs, along with a local centre, primary school, open space and supporting infrastructure.

The planning framework includes a State Environmental Planning Policy (SEPP) amendment and approval of the Precinct Structure Plan and Development Control Plan (DCPs).

These final plans were refined following public exhibition in 2025. The Department considered 46 submissions from the community, Wollondilly Shire Council, Campbelltown City Council and NSW Government agencies.

Amendments to Precinct Structure Plan include:

  • increasing the primary school site from 2.4 hectares to 3 hectares
  • improving the open space network and recreation areas
  • adding two new koala crossings and strengthening protection of the Ousedale Creek koala corridor
  • the Appin Bypass alignment was refined to reduce impacts on environmentally sensitive land and improve biodiversity outcomes.

Key issues raised during consultation included infrastructure capacity, koala habitat and bushfire risk. Feedback from the community, councils and government agencies informed a range of updates to the final plans.

To support implementation of the precinct, the Department has prepared a comprehensive Wollondilly Greater Macarthur Growth Area DCP, which consolidates the exhibited DCPs for the Appin (Part) Precinct and North Appin (Part) Precinct into a single planning framework. This provides greater consistency and clarity across the Wollondilly portion of the Greater Macarthur Growth Area and aligns with relevant state planning frameworks and guidelines.

A separate North Appin (Part) Precinct DCP has been prepared for the small portion of the precinct within the Campbelltown local government area. This ensures a consistent planning framework applies across the entire North Appin (Part) Precinct while reflecting the different local government boundaries.

The final plans can be viewed on the NSW Planning Portal.

View the plans

Community consultation

A planning proposal, draft DCP and draft Precinct Structure Plan prepared by Ingham Property Group were available for public feedback from Monday 8 September to Monday 6 October 2025.

The plans were exhibited concurrently with the Appin (Part) Precinct plans. This included the planning proposal seeking to rezone the land, draft DCP and draft Precinct Structure Plan prepared by Ingham Property Group. This ensured all relevant information for the 2 major projects in the Appin area was available at the same time.

A face-to-face community drop-in session was held on Tuesday 23 September 2025 from 4 pm to 6:30 pm.

The Department reviewed 46 submissions from the community, Wollondilly Shire Council, Campbelltown City Council and NSW Government agencies.

What happens next

As the plans are approved, development applications can now be lodged in accordance with the approved planning framework.

A state planning agreement will also need to be prepared to deliver infrastructure to support the new homes.

For any enquiries, email the Southern Western and Macarthur team at [email protected]

What is planned for North Appin (Part) Precinct

The North Appin (Part) Precinct was rezoned on 27 October 2026. Find out more about the North Appin (Part) Precinct rezoning on the NSW Planning Portal.

The North Appin (Part) Precinct covers around 301 hectares of land along Appin Road and forms part of the Greater Macarthur Growth Area.

The final plans will support around 3,000 new homes and approximately 670 local jobs, supported by a mix of housing, a local centre, a primary school, open space and essential infrastructure.

A dwelling cap of 2,499 homes will apply across the Appin (Part) Precinct and North Appin (Part) Precinct until supporting infrastructure becomes available.

Environmental conservation is a key feature of the precinct, with approximately 60 hectares of land protected for conservation, including part of the Ousedale Creek koala corridor. The plans also include dedicated koala crossings and other measures consistent with the Cumberland Plain Conservation Plan.

Development will occur over several stages, guided by a staging plan that coordinates housing delivery with infrastructure, public open space and community facilities.

A primary school is planned for a later stage of development as the local population grows. Funding has been committed to support infrastructure required for the early stages of development.

With the planning framework now in place, including the Precinct Structure Plan and DCP, future development applications can be assessed in accordance with the approved plans.

Frequently asked questions

Where is the North Appin (Part) Precinct?
Greater Macarthur growth area Appin (part) precinct plan land application map
Greater Macarthur Growth Area – Appin (Part) and North Appin (Part) Precincts land application map
How will infrastructure be delivered in North Appin?

Significant investment is required to upgrade regional wastewater and transport networks to support growth in the Greater Macarthur Growth Area. Planning for North Appin has been designed to ensure essential infrastructure is delivered alongside new homes.

While the North Appin (Part) Precinct has capacity for around 3,000 homes over the long term, development will occur in stages. A dwelling cap of 2,499 homes currently applies across the Appin release areas, including North Appin, based on available infrastructure capacity and committed upgrades. This ensures housing delivery is aligned with essential infrastructure and agreed funding arrangements.

The cap will only increase as additional infrastructure capacity becomes available and delivery pathways are confirmed.

The Department is working closely with Sydney Water, NSW Government agencies, councils and developers to ensure water, transport and community infrastructure are delivered to support growth. This includes investigating interim and long-term wastewater solutions.

Key infrastructure includes:

  • road upgrades and transport connections
  • stormwater infrastructure, including 11 detention basins
  • a primary school site
  • parks, sports fields and public open space.

Infrastructure will be delivered in stages, as outlined in the development staging plan. Roads and open space will come early, with schools added as the population grows. Funding is already committed for the early stages.

What is the Precinct Structure Plan and Development Control Plan?

The Precinct Structure Plan shows where homes, shops, parks, conservation areas, and infrastructure could go.

The Development Control Plan outlines proposed planning controls that will apply to homes, subdivisions and non-residential development.

What is a Transport Management and Accessibility Plan?

Inghams Property Group worked with Transport for NSW, Wollondilly Shire Council and the Department to prepare a Transport Management and Accessibility Plan for the North Appin (Part) Precinct to provide an overarching framework for the implementation of essential transport infrastructure and services to support development.

The final Transport Management and Accessibility Plan was endorsed by Transport for NSW on 20 April 2026. Inghams Property Group then used the Transport Management and Accessibility Plan findings to inform the rezoning, Development Control Plan and Precinct Structure Plan.

How are koalas being protected in North Appin?

The plans include approximately 60 hectares of environmental conservation land, including part of the Ousedale Creek koala corridor.

The final plans introduce two dedicated koala crossings and refined transport corridor alignments to minimise impacts on habitat and wildlife movement.

Future development must comply with environmental controls and conservation measures under the Cumberland Plain Conservation Plan.